MACKINAC BRIDGE PROJECTS - 2007 THROUGH 2011








PROJECT


DESCRIPTION


TIME FRAME


TRAFFIC DELAYS








Bridge repainting project


Complete paint removal and reapplication of primer and surface paint.


Ongoing all season for years 2006, 2008-2011.


Area lane closures Monday through Friday. Some overnight closures. Weekend lane closures as traffic levels permit.








Bridge deck resurfacing


Mill off old bituminous and replace.


Fall of 2006 and spring of 2007.


Traffic switch with two way traffic. Possible delays northbound on Fridays and southbound on Sundays.








Catwalk improvements


Install maintenance catwalks along perimeter of truss approaches.


Ongoing all season during summer of 2009-2010.


Daytime and some overnight lane closures Monday through Friday. Weekend lane closures as traffic levels permit.








Cross beam repair


Repair deteriorated cross beams under the bridge roadway.


Ongoing all season during summer of 2006.


Daytime lane closures Monday through Friday.








Main cable inspection


Thoroughly inspect sections of the main cables near the top of the towers.


During the month of July in 2007.


Area lane closures Monday through Friday. Temporary traffic stoppages of 20 minutes or less.

Deck grating replacement


Remove and replace sections of open grating on the suspended spans.


2007-2011


Day and night time lane closures Monday through Friday.

Causeway resurfacing


Mill and replace the bituminous surface on the causeway.


Spring of 2010


Traffic switch with two way traffic. No weekend lane closures.

Tower hanger replacement


Remove and replace the tower links.


2010-2011


Traffic switch with two way traffic.

Viaduct bearing replacement


Remove and replace the bearings on the 13 south viaduct spans.


Ongoing all season during summer of 2007.


Day and night lane closures all week.